2024 RFP: Frequently Asked Questions


2024-General

2024-GEN 00007
Published On: 07/26/2024

Question: Can you confirm the following requirement applies only for UOT track proposals and not for PPA track proposals? "Bidders are expected to provide valid due diligence terms through mid-2028 (July), or longer, with a minimum of 18 months of a construction term and a minimum of 35 years of an operating term commencing at placed in service (if lease agreement);"

Answer: This requirement is listed in Section IV.A of the 2024 RFP, which only applies to UOT proposals.

2024-GEN 00006
Published On: 07/24/2024

Question: Can an MP submit a project under the UOT that does not meet the site control requirements outlined in Section IV.A of the 2024 RFP, provided that the project has a signed interconnection agreement from a previous serial process and the site due diligence term is sufficient to achieve the ISD under the interconnection agreement? I.e., can an MP submit a project that has site control through 2027, if the project COD is 2027?

Answer: Yes, an MP may bid a project into the UOT track that has site control through 2027; however, the proposal will be scored accordingly. Site control requirements are provided in “Section IV Proposal Tracks, A. Utility Ownership Track Proposal” bullet 6 -

"Provide sufficient and satisfactory site control rights for the Facility including delivery to the Point of Interconnection (POI) to develop and construct the proposed Facility within the timeframe laid out in the RFP. Bidders are expected to provide valid due diligence terms through mid-2028 (July), or longer, with a minimum of 18 months of a construction term and a minimum of 35 years of an operating term commencing at placed in service (if lease agreement);”.

There are other factors beyond just a fully executed interconnection agreement that may impact a project’s construction lead time, such as equipment availability, construction subcontractor availability, outage coordination, etc. As such, all UOT projects will be scored in accordance with the requirements provided.

2024-GEN 00005
Published On: 07/17/2024

Question: Is the maximum size project allowed to bid into this RFP 80 MWac? Will projects larger than 80 MW not be allowed?

Answer: For a power purchase agreement (PPA) track project, the maximum size is up to and including 80 MWac (based on the interconnection request) in both DEC and DEP. However, projects bidding into the Utility Ownership Track (UOT) of the RFP can be larger than 80 MWac (and any project greater than 80 MWac would be submitting their interconnection request as a FERC jurisdictional project).

2024-GEN 00004
Published On: 07/16/2024

Question: I’m trying to understand whether bat studies are required prior to RFP submission or only if the project is selected in the [2024] RFP. The RFP requirements and FAQ GEN 00070 on https://www.dukeenergyrfpcarolinas.com/FAQ/General contradict each other. Thanks in advance for clarifying. From the tariff: UTILITY OWNERSHIP TRACK PROPOSALS In addition to the requirements in Section III, Proposals for Facilities in the Utility Ownership Track must also meet all of the following: Include a habitat assessment and onsite acoustic survey for all listed and proposed to be listed bat species, as well as any bat species listed or proposed to be listed after the issuance of this RFP within bidder scope. Duke Energy, as project owner, shall have the ability to review and approve the scope of said studies before authorized. The U.S. Fish and Wildlife Service ("USFWS") has listed or proposed to be listed several bats species with habitat range in North and South Carolina. These species include the Indiana Bat (Myotis sodalist) and Northern Long-eared Bat (Myotis septentrionalis), both currently listed as endangered. The tricolored bat (Perimyotis subflavus) is proposed to be listed in the fall of 2023 as either a threatened or endangered species.

Answer: To clarify the guidance provided in GEN 00070 and 00007 for the 2023 RFP, for Asset Transfer and BOT bids, the Seller (the Market Participant) will be required to complete habitat assessment(s) and onsite acoustic survey(s), as established in Section IV.A. This will be the responsibility of the Market Participant and must be completed, along with all other applicable scope, as a condition to close pursuant to the applicable definitive agreement (Asset Purchase Agreement or Build Transfer Agreement). So, the assessment and surveys do not need to be completed prior to bidding a project into the RFP.

2024-GEN 00003
Published On: 07/16/2024

Question: Is the habitat assessment and acoustic survey for bats required prior to RFP submission for UOT projects? Considering the changing habits of bats which often change roosts seasonally, can it be assumed that a habitat assessment and acoustic survey will be required every year for the same project?

Answer: The habitat assessment and onsite acoustic survey requirements established in Section IV.A of the RFP, which apply to Utility Ownership Track projects, are not required to be completed prior to bid submission. The RFP provides guidance for bidders to plan to complete the habitat assessment and an onsite acoustic survey as part of their scope submission; whether and how often an assessment or survey will be required to be updated will depend on project specifics and then-current rules and regulations .

For additional information please see 2024-GEN 00003 and Q&As from the 2023 RFP - GEN00006, GEN00007 and GEN 00070.

2024-GEN 00002
Published On: 07/10/2024

Question: To clarify, for the 2024 RFP only the UOT proposals need to submit a habitat and onsite acoustic survey for all listed and proposed to be listed bat species, correct? PPA proposals are not required to submit that bat species information?

Answer: Correct, the habitat assessment and onsite acoustic survey requirements estimated in Section IV.A of the RFP only apply to Utility Ownership Track projects.

For additional information please see GEN00006, GEN00007 and GEN 00070, available at www.dukeenergyrfpcarolinas.com/FAQ/General.

2024-GEN 00001
Published On: 06/17/2024

Question: This question is regarding the upcoming 2024 RFP. Will Duke permit projects on local coop infrastructure to wheel power to them in this RFP?

Answer: Facilities must be located in the Duke Energy Carolinas (DEC) or Duke Energy Progress (DEP) North Carolina or South Carolina service territory and will physically interconnect with the DEC or DEP transmission system.