2025-STM 00003 Published On: 04/15/2025
Question: During the call on April 9, a “Tranche 1 report from 2024 RFP” was provided in chat. The provided pdf document actually appears to be dated 2019. Wondering if the wrong doc was attached? Is there a 2024 document that can be shared?
Answer: The link provided during the stakeholder meeting was to a 2019 CPRE report, not a 2024 RFP report. The latest RFP report from August 2024 is available at https://www.dukeenergyrfpcarolinas.com/RFP-Documents.
2025-STM 00002 Published On: 04/15/2025
Question: Is there any preference for SPS projects (hybrid vs co-located)?
Answer: Using the NERC definitions of these terms, the Companies are seeking co-located facilities.
2025-STM 00001 Published On: 04/15/2025
Question: There was a request on the 1/29/2025 stakeholder call for comments to the pro forma documents. Which documents should stakeholders be using as the baseline?
Answer: 2025 RFP documents are not yet available. The Companies plan to use the 2024 RFP documents as a starting point, these are available on the IE’s website in the 2024 documents section - www.dukeenergyrfpcarolinas.com/2024-RFP-Documents. The slide deck from the 2025 Stakeholder Engagement session is also available on the IE’s website at https://www.dukeenergyrfpcarolinas.com/StakeholderMaterials.