2025 RFP: Frequently Asked Questions


2025-General

2025-GEN 00009
Published On: 06/13/2025

Question: For a project submittal into the 2025 UOT, ALTA surveys that appear to meet Duke Survey requirements are completed, but were performed by a survey firm that is not listed in the "2025 RFP Appendix L-UOT Survey Requirements Attachment 2 Approved MSA Vendors". Is there a recommended course of action for remedying this in lieu of a complete resurvey?

Answer: Asset Transfer proposals are expected to comply with the provided requirements. That being said, if a market participant has an existing survey completed, Duke Energy is willing to review the survey and evaluate if acceptable and can provide comments if the survey is not satisfactory.

2025-GEN 00008
Published On: 06/13/2025

Question: I posed a previous question regarding eligibility of solar only projects sited in coop service territory able to connect directly to a DEP/DEC transmission line. I did not receive confirmation of a response to my question, but 2025-GEN 00004 appears to be a partial answer. It references special circumstances for grid charged batteries. To clarify further, are solar-only projects that pursue a utility transfer track of permitting and interconnection eligible even if the project is not in Duke service territory but connects to a Duke line and is in the Carolinas? In addition, how will auxiliary power be treated for the solar only project that is in coop service territory but connects to a DEP line? Will auxiliary power be considered a purchase by the project requiring the coop to provide service at the site or will aux power by netted out of the generation produced by the project?

Answer: Please see the response posted for 2025-GEN 00005. 

2025-GEN 00007
Published On: 05/22/2025

Question: We would like to know what is Duke's policy on co-locating Qualified Facilities, where two projects are located next to each other? Would a phased approach for the two projects be possible through Qualified Facilities process? If two Qualified Facilities projects cannot be sited next to each other, could there be two adjacent projects (80 MW and 65 MW) that are not Qualified Facilities?

Answer: The FERC policy on Qualifying Facilities is that Qualifying Facilities within one mile of each other are deemed to be at the same site and their capacity is aggregated to determine whether they meet the 80 MW or less threshold for small power production QFs.  Two QFs could be sited less than one mile from one another as long as the combined capacity is less than 80 MWs.  If facilities are sited less than one mile from each other and the combined capacity is greater than 80 MW, then they would not qualify as QFs under FERC federal law.  For facilities that would not qualify as QFs under FERC federal law, FERC has jurisdiction over their interconnections and they would be eligible for the Utility Ownership Track of the RFP. For further clarity please see the 2024 RFP, p.13-14 for explanation.    

2025-GEN 00006
Published On: 05/20/2025

Question: Could you please confirm whether 100-ft setbacks are required only for UOT proposals, or for PPA proposals as well?

Answer: The technical guidance in Appendix I-1, including setback requirements, is applicable to UOT Proposals only.

2025-GEN 00005
Published On: 05/06/2025

Question: Did the site location eligibility intentionally change from the 2024 RFP? The 2024 RFP restricted projects to sites within Duke service territory. The 2025 RFP restricts projects to sites in North or South Carolina. (In both cases, the project must interconnect with a Duke transmission line.) Can you confirm a project site in South Carolina in a coop service territory is eligible IF the project physically interconnects with the DEC or DEP transmission system.?

Answer: A solar-only project located in South Carolina in another utility’s service territory is eligible for the 25 RFP if the project physically interconnects with the DEC or DEP transmission system. Pursuant to the 25 RFP solar-only PPAs, “Seller shall be responsible for arranging and obtaining, at its sole risk and expense, any station service [Station Power] required by the Facility.” However, a SPWS project must be eligible to receive service from DEP or DEC in order to grid-charge from the DEC or DEP system.

2025-GEN 00004
Published On: 04/28/2025

Question: Will projects outside Duke service territory capable of delivering into Duke be eligible for bid?

Answer: All facilities in the RFP, including facilities sited outside of Duke's service territory, must directly interconnect to the DEC or DEP transmission system. Solar paired with Storage facilities shall also be responsible for ensuring their site is eligible to receive electric service from DEP or DEC for grid-charging.

2025-GEN 00003
Published On: 04/28/2025

Question: 1. Can you confirm that Duke WILL accept Surety Bonds for Step 2 Proposal Security? 2. For the UOT track, will Surety Bonds be accepted as a final deposit and/or later in the RFP process should a Project move forward, or is there a point at which Surety is no longer acceptable and LOC is required? Any additional clarification that can be provided on Surety would be appreciated.

Answer: Surety bonds are an acceptable form of security for Step 2 proposal security for both tracks. The form acceptable is included in Appendix D. Surety bonds are not accepted for the Power Purchase Agreement’s Performance Assurance due within 5 days of signing the contract.

2025-GEN 00002
Published On: 04/15/2025

Question: We had a question regarding co-located projects submitting into the Duke RFP. If a co-located project is selected to enter the RSC, would the project need to submit two separate queue positions, or can it submit a single queue position for the entire project?

Answer: A “co-located” solar paired with storage project still has only 1 point of interconnection. A project that chooses to bid both solar-only and solar paired with storage will only submit one interconnection request, which is the same approach as the 2023 and 2024 RFPs.

2025-GEN 00001
Published On: 04/15/2025

Question: Any idea yet of what initial bid fees/ security postings will look like when the RFP is filed?

Answer: For the 2025 RFP, the Companies will share draft documents in April 2025 and as of early March, there are not yet proposed changes to the bid fee structure or security postings from the 2024 RFP. 2025 RFP Stakeholder meetings are still ongoing, the next session is planned for March 11.